Google has halted what Belgian authorities called the “illegal construction” of an artificial intelligence data centre in Farciennes. The US technology company said it had paused the works “pending additional guidance”.
The firm is accused of lacking the correct planning permission, which Wallonia government spokesperson Nicolas Yernaux described as a “major offence”. In a statement, Google said it had operated in Belgium for over 15 years and remained committed to complying with local laws.
Dispute over cooling system and planning permission
The project has been locked in litigation for months after Google applied to amend the terms of its planning permission. According to local media, the company wanted to replace its proposed air cooling with a system that would draw water from the nearby River Sambre.
Regional officials refused that application, but work on the site continued. This prompted concerns from people living nearby and from environmental groups.
Environmental groups criticise continued building
Joeri Thijs of Greenpeace Belgium said: “That Google continues to build without a permit is disrespectful to the environment, local residents, and the law.” He added that energy-guzzling data centres “cannot remain under the radar” as the climate crisis worsens.
A court hearing is scheduled to take up the case in the new year.
Growing backlash against data centres
Opposition to data centres is growing across the world over their energy use. Data Center Map, which tracks operational and pre-operational sites, counts around 13,500 data centres globally, with 54 in Belgium.
The US has more than 5,200, the most of any country. Their spread became a major issue in the mid-term elections, where three states elected Democrat senators and governors who called for tighter regulation of data centres.