Prime Minister Shehbaz Sharif has called for a Pakistan that is economically strong, independent in energy and resilient to environmental pressures. He made the remarks on Tuesday in Mianwali, where he spoke at the dome placement ceremony for the Chashma-5 Nuclear Power Plant (C-5). He said the country would use its resources, technology and people to secure a prosperous future.
The prime minister described the milestone as proof of Pakistan’s resolve to shape its own direction through hard work, technical progress and strategic partnerships. He argued that Chashma-5 was about far more than construction materials. In his view, it represents a commitment to clean, dependable and affordable electricity that will support the national economy and improve daily life.
Dome milestone and the push for energy security
Sharif said nuclear power would reduce Pakistan’s reliance on imported fuels and the swings of international prices. He added that a steady supply would reach industries, hospitals, schools and households.
Recalling his pledge at the groundbreaking in July 2023, he said that “Pakistan will not wait for anyone”. He noted with satisfaction that the dome was installed less than three and a half years after groundbreaking, ahead of schedule. He also expressed confidence that the project would be commissioned earlier than planned.
The prime minister stressed that Pakistan, as a climate-vulnerable country, had a particular duty to pursue energy solutions that drive development while protecting the environment. He also said no nation could build a prosperous future without first safeguarding its present.

Nuclear output and key plant figures
Earlier at the event, the chairman of the Pakistan Atomic Energy Commission (PAEC) outlined nuclear energy’s growing role in the national electricity mix and energy security. He said the country’s nuclear plants were generating 3,530 megawatts safely and efficiently. He added that this helps avoid about 15 million tonnes of carbon dioxide emissions each year.
The PAEC chairman shared several figures on the sector and the new project:
- Nuclear energy supplies around 16.6% of Pakistan’s electricity generation.
- It accounts for only 8.6% of installed power capacity.
- Its share rises to roughly 26% during winter.
- Chashma-5 will have a generation capacity of 1,200 megawatts.
- The plant is expected to begin producing electricity in September 2030.
Armed forces, China ties and CPEC cooperation
Sharif credited the armed forces, led by Chief of Army Staff and Chief of Defence Forces Field Marshal Syed Asim Munir, with ensuring security and stability. He praised the professionalism, courage and resolve of the forces during Marka-e-Haq. He said a secure environment was essential for attracting investment, reviving the economy and speeding up socioeconomic development. He also thanked CDF Munir for backing the government’s economic revival and development initiatives.
The prime minister presented Chashma-5 as another lasting sign of the all-weather friendship between Pakistan and China. He said it is the seventh nuclear power unit China has helped Pakistan build. He thanked Chinese President Xi Jinping, the Chinese government and the China National Nuclear Corporation for their continued support. He also recognised engineers from both countries.
Sharif further said the second phase of the China-Pakistan Economic Corridor (CPEC) would open new economic opportunities and strengthen strategic ties. He congratulated the PAEC, the China Atomic Energy Authority, the China National Nuclear Corporation, contractors, financial institutions and other stakeholders. He also thanked the people of Mianwali for hosting the project. He expressed hope that Chashma-5 would remain a symbol of friendship and shared goals of peace, stability and prosperity.